JTUS, Vol. 03, No. 6 June
2024
E-ISSN: 2984-7435, P-ISSN: 2984-7427
DOI:
https://doi.org/10.58631/jtus.v3i6.100 |
1,2,3Institut Teknologi Bandung, Bandung, West Java,
Indonesia
E-mail: 25022020@mahasiswa.itb.ac.id1, 25022014@mahasiswa.itb.ac.id2, [email protected]3
Abstract Construction productivity measures the output generated
in the construction process using available resources. In the Indonesian Construction
Industry, construction is
often carried out inefficiently, resulting in high construction costs, prolonged durations, and substantial waste, leading to low levels
of construction productivity. This study aims to enhance
construction effectiveness
through planning and management aided by model simulations, specifically targeting slab work operations at the Conggeang
Bridge Project - Cisumdawu
Toll Road Section 5A. The modeling simulation
in this study utilizes the CYCLONE model with the assistance of EZSTROBE/STROBOSCOPE and
SIMULINK software. This approach provides data on productivity, utilization factor, and average wait
time for the operations under review. Based on the
obtained data, a productivity
and sensitivity analysis is conducted
to identify several alternative improvements in the execution of slab work operations
on this bridge. The proposed improvements aim to reduce construction
costs, implementation duration, and generated waste, thereby increasing overall construction productivity. Keywords: Construction, Productivity, Construction Operation, CYCLONE, EZSTROBE,
SIMULINK. |
INTRODUCTION
Currently, the Indonesian construction industry and various parts
of the world
are still experiencing inefficiencies in the implementation of the construction process
The
amount of waste that occurs
in the construction process is a problem that needs special
attention from construction actors because this will
impact the use of time
& space during the construction process, which also impacts the
cost of completing
the project. One of the solutions
offered in reducing waste in the construction
process is to increase productivity;
this is because
productivity can be used as a parameter in determining inefficiency & efficiency during the implementation of the construction
process. Productivity that has a high value shows the
greater the profit obtained by the
contractor
In
this study, we will analyze the
Conggeang – Cisumdawu Bridge Project Section 5A. The operation to be
analyzed in this project is slab
work. The selection of slab work
is because this operation is one of
the operations that affects the
implementation of the bridge
This
study aims to simulate slab operations,
conduct productivity and sensitivity analysis based on modeling carried out on slab
operations, and provide alternative solutions for slab
operations based on productivity levels, utilization factors, and average
time waits.
METHODS
This
research begins by determining the research background,
identifying problems, and formulating goals. Furthermore, a literature review was carried out
regarding the problems raised. The next stage is
the collection of the required
data. After the data is collected, it is
continued at the CYCLONE modeling and model simulation stage using software. In this stage, the
data is analyzed to determine the
CYCLONE model according to the conditions in the field, which
will then be simulated with
the help of Simulink and
Stroboscope software. After
the simulation is successful, the stage continues
by conducting a sensitivity analysis that is expected
to result from the software
and sensitivity analysis to be
able to provide
productivity values as well as solutions, alternatives, or recommendations for a construction operating system
RESULTS AND DISCUSSION
Operations Modeling
Assumptions Used
The
modeling of slab work in this study was carried out
based on the following assumptions:
the cycle for modeling slab work was measured
based on 1 span of bridge, which
requires 2 bondek trucks, 8 rebar trucks, 2 formwork trucks, and 22 mixer trucks to
meet the volume of 1 span of 127.5 m³. It is also
assumed that the laborer resources
are already in the form of a team
of 3 people.
Identify the
Duration and Resource Work Task
Work
tasks in CYCLONE modeling are tasks
or work that
need to be
done in the modeling that is carried
out
In addition,
before modeling CYCLONE, it
is necessary to identify the
resources that will be used
in slab modeling
Table 1. Duration
and Resource Work Task
ID |
Work Task |
PDF |
Duration |
Resource |
Quantity |
||
a |
m |
b |
|||||
WT 1 |
Load Bondex to Truck on Supplier |
Deterministic |
20 |
Bondex Truck 1 (Bondex) |
1 2 |
||
WT 2 |
Travel Bondex to Stockyard |
Triangular |
30 |
45 |
50 |
Truck 1 (Bondex) |
2 |
WT 3 |
Unload Bondex to Stockyard |
Deterministic |
20 |
Laborer Truck 1 (Bondex) |
2 2 |
||
WT 4 |
Truck Return to Load Bondex |
Triangular |
30 |
45 |
50 |
Truck 1 (Bondex) |
2 |
WT 5 |
Move Bondex to Site |
Triangular |
7 |
10 |
15 |
Bondex Truck 2 (Bondex) |
1 2 |
WT 6 |
Load Bondex to Winch |
Deterministic |
10 |
Bondex Crane Space |
1 1 2 |
||
WT 7 |
Lifting Bondex to Bridge |
Deterministic |
10 |
Crane |
1 |
||
WT 8 |
Remove Bondex from Winch |
Deterministic |
10 |
Laborer Crane |
4 1 |
||
WT 9 |
Install Bondex |
Triangular |
150 |
200 |
250 |
Laborer Bondex |
4 1 |
WT 10 |
Load Iron to Truck on Supplier |
Triangular |
5 |
10 |
15 |
Iron Truck 1 (Iron) |
1 8 |
WT 11 |
Travel Iron to Stockyard |
Triangular |
10 |
15 |
20 |
Truck 1 (Iron) |
8 |
WT 12 |
Unload Iron to Stockyard |
Triangular |
5 |
10 |
15 |
Laborer A Truck 1 (Iron) |
1 8 |
WT 13 |
Truck Return to Load Iron |
Triangular |
10 |
15 |
20 |
Truck 1 (Iron) |
8 |
WT 14 |
Barbending |
Triangular |
180 |
240 |
270 |
Iron Laborer A |
1 1 |
WT 15 |
Load Iron to Truck on Stockyard |
Triangular |
5 |
10 |
15 |
Iron Hydraulic Truck 2 (Iron) |
1 1 2 |
WT 16 |
Travel Iron to Site |
Triangular |
5 |
10 |
15 |
Truck 2 (Iron) |
2 |
WT 17 |
Load Iron to Crane |
Triangular |
5 |
10 |
15 |
Crane Truck 2 (Iron) |
1 2 |
WT 18 |
Truck return to Stockyard |
Deterministic |
10 |
Truck 2 (Iron) |
2 |
||
WT 19 |
Install Iron |
Triangular |
180 |
240 |
300 |
Laborer C Iron |
1 1 |
WT 20 |
Load Formwork Material to
Truck on Supplier |
Triangular |
7 |
15 |
20 |
Formwork Truck 1 (Bekisting) |
1 2 |
WT 21 |
Travel Formwork Material to Stockyard |
Triangular |
20 |
30 |
45 |
Truck 1 (Bekisting) |
2 |
WT 22 |
Unload Formwork Material to
Stockyard |
Triangular |
10 |
20 |
30 |
Laborer A Truck 1 (Bekisting) |
1 2 |
WT 23 |
Truck Return to Load Formwork Material |
Triangular |
20 |
30 |
45 |
Truck 1 (Bekisting) |
2 |
WT 24 |
Formwork Fabrication |
Triangular |
180 |
240 |
300 |
Formwork Laborer A |
1 2 |
WT 25 |
Load Formwork to Truck on Stockyard |
Triangular |
20 |
30 |
40 |
Formwork Laborer A Hydraulic Truck 1 (Bekisting) |
1 1 1 2 |
WT 26 |
Travel Formwork to Site |
Deterministic |
7 |
Truck 1(Bekisting) |
2 |
||
WT 27 |
Lifting Formwork to Bridge |
Deterministic |
15 |
Truck 1(Bekisting) Laborer B Crane |
2 1 1 |
||
WT 28 |
Install Formwork |
Triangular |
200 |
260 |
320 |
Formwork Laborer B |
1 1 |
WT 29 |
Load Concrete to Truck on Batching
Plant |
Deterministic |
20 |
Concrete Truck 1 (Concrete) |
1 7 |
||
WT 30 |
Travel Concrete to Site |
Triangular |
30 |
45 |
60 |
Truck 1 (Concrete) |
7 |
WT 31 |
Maneuver to Position to Dump Concrete |
Deterministic |
10 |
Avail Post Truck 1 (Concrete) |
2 7 |
||
WT 32 |
Dump Concrete |
Triangular |
20 |
25 |
30 |
Hooper Truck 1 (Concrete) |
1 7 |
WT 33 |
Position Depart |
Deterministic |
10 |
Truck 1 (Concrete) |
7 |
||
WT 34 |
Truck Return to Batching Plant |
Triangular |
30 |
45 |
60 |
Truck 1 (Concrete) |
7 |
WT 35 |
Concrete Pumping |
Deterministic |
15 |
Hooper Truck 1 (Concrete) |
1 7 |
||
WT 36 |
Slab Casting |
Triangular |
30 |
60 |
120 |
Laborer |
2 |
CYCLONE Modeling
CYCLONE
modeling or simulation in construction operations analysis is the
process of using mathematical or computer tools
and techniques to replicate and
predict the performance and outcomes of construction
projects
Figure 1. CYCLONE Operation Slab
Work of Conggeang
Bridge Project
Analysis of
Simulation Results
This
study simulates several cycles to get
productivity where the simulation produces a relatively small productivity variation over time. The productivity value obtained is productivity
for one span (one cycle)
EZSTROBE Result Analysis
In
the simulation using EZSTROBE software, the value of
the time required in 1 cycle (1 cycle = 1 span) was obtained as 6231.22 minutes or 103.853 hours. Based on this
value, the productivity value of the cycle
can be determined
using the formula below
Based on the
calculation above, it can be
known that the productivity value of slab
work for each span is 0.00963 with the time
of each cycle
is 103.853 hours. In addition, this slab work consists
of 15 spans so the total time
needed to complete the entire
slab work is 1557,805 hours or 64.9 days. The following has been included the data from the model test using EZSTROBE software in Appendix B: EZSTROBE Analysis
Results
Analysis of
SIMULINK Simulation Results
In
the simulation using SIMULINK software, the value of
the time required in 15 spans (1 cycle = 1 span) is obtained of 74273 minutes or 1237.88 hours so that
the time per cycle can be
obtained by dividing the total time by the
number of spans (15), which is 82.5255 hours. Based on this
value, the productivity value of the cycle
can be determined
using the formula below.
Based on the
calculation above, it can be
known that the productivity value of slab
work for per span is 0.01211 with the time of
each cycle is 82.55 hours. In this slab work
consists of 15 spans so the
total time needed to complete the
entire slab work is 1237.88 hours or 52 days.
Here is a graph regarding the productivity
& cycle time of slab work.
Figure 2. Slab Job Productivity
From the
graph of the Simulink simulation
results, you can see the
productivity value.
Figure 3. Slab Job Cycle Time
In addition
to productivity & cycle time, there
are other indicators in
SIMULINK used in this
study, namely:
1. Resource utilization
useful for determining the intensity of the
use of resources
involved in the process
2. Resource average
wait (idle time), useful for
knowing the wait time of
the resources involved in the process
Here
is a combined graph of the
resource utilization and idle time
of the 4 processes on the
slab job. The graph of resource
utilization and idle time for
each bondex installation, slab repetition, side formwork installation, and slab casting
work is found
in Appendix C: SIMULINK Analysis
Results.
Figure 4. Resource Utilization Slab
Work
Figure 5. Average Wait
Resources Slab Jobs
Bondek Installation
In
the resource utilization graph, it can be
seen that there are several resources in the Bondek installation process that have
a resource utilization value below 0.5
Slab Ironing
In
the resource utilization graph, it can be
seen that there are several resources in the slab ironing process
that have a resource utilization value below 0.5, such as laborer 4 & truck 3. This shows
that the use of these
two resources is not efficient. In addition, some resources with a value of 1 can
be re-optimized by increasing the
number of resources so that
the construction process runs more
effectively
Installation of
Side Formwork Slab
In
the resource utilization graph, it can be
seen that the indication of resource utilization
begins to stabilize when entering the 20000 minutes
Slab Casting
In
the resource utilization graph, it can be
seen that the indication of resource utilization
starts to stabilize when entering the 30000th minute and it
is known that resources pos1 has the smallest utilization
value compared to other resources.
This shows that these resources
have the lowest efficiency so it is
necessary to re-plan the number
of resources
Comparison of
Simulation Productivity with Field Data
The
following is the result of
comparing data on productivity & cycle time in modeling in EZSTROBE & SIMULINK software with the
reality in the field from January-March
(75 days).
Table 2. Comparison of Simulation Results with Field
Comparison |
|
|||
Category |
EZSTROBE |
SIMULINK |
Field |
|
Productivity |
0,00963 |
0,01211 |
0,0083 |
|
Cycle Time |
103,853 |
82,52 |
120 |
|
From the
table, it can be seen
that the productivity of the simulation results using ezstrobe
and Simulink is different from
the field data. This can be
because, in the field, there are still holidays or non-working days, but they
are still included in the total number of days of
slab work.
Sensitivity Analysis
Sensitivity Analysis is the
process of understanding and evaluating the impact of changes
in certain variables on the system
Table 3. CYCLONE Sensitivity
Analysis Operation Slab Work Conggeang
Bridge Project
Existing
Conditions |
Iteration
1 |
Iteration
2 |
Iteration
3 |
||||||||||
Resource |
Sum |
Utilization |
Average
Wait (Min) |
Sum |
Utilization |
Average
Wait (Min) |
Sum |
Utilization |
Average
Wait (Min) |
Sum |
Utilization |
Average
Wait (Min) |
|
Supplier bondex |
1 |
39.4% |
76.04 |
100.0% |
60.2 |
1 |
100.0% |
60.2 |
1 |
100.0% |
60.2 |
||
Bondex trailer |
2 |
100.0% |
76.04 |
4 |
100.0% |
60.2 |
5 |
80.0% |
60.2 |
5 |
80.0% |
60.2 |
|
Labor Team A |
1 |
100.0% |
378.9 |
2 |
100.0% |
345.8 |
2 |
100.0% |
345.8 |
2 |
100.0% |
345.8 |
|
Labor Team B |
1 |
100.0% |
264.9 |
2 |
100.0% |
229.5 |
2 |
100.0% |
229.5 |
2 |
100.0% |
229.5 |
|
Supplier Iron |
1 |
100.0% |
59.92 |
1 |
100.0% |
59.92 |
1 |
100.0% |
59.92 |
1 |
100.0% |
59.92 |
|
Truck B |
8 |
50.0% |
59.92 |
8 |
50.0% |
59.92 |
16 |
25.0% |
59.92 |
16 |
25.0% |
59.92 |
|
Labor Team C |
3 |
69.2% |
531.3 |
4 |
51.9% |
531.3 |
4 |
51.9% |
531.3 |
4 |
51.9% |
531.3 |
|
Labor Team D |
1 |
8.5% |
180 |
2 |
4.3% |
173 |
2 |
4.3% |
173 |
2 |
4.3% |
173 |
|
Labor Team E |
2 |
33.7% |
8.8 |
3 |
22.2% |
13.1 |
3 |
22.2% |
13.1 |
3 |
22.2% |
13.1 |
|
Supplier Formwork |
1 |
53.4% |
83.82 |
1 |
53.4% |
83.82 |
1 |
100.0% |
83.82 |
1 |
100.0% |
83.82 |
|
Trailer Formwork |
2 |
100.0% |
83.82 |
2 |
100.0% |
83.82 |
4 |
100.0% |
83.82 |
4 |
100.0% |
83.82 |
|
Labor Team F |
3 |
85.4% |
490.4 |
4 |
63.2% |
489.8 |
4 |
63.2% |
489.8 |
4 |
63.2% |
489.8 |
|
Labor Team G |
2 |
3.2% |
225.3 |
3 |
2.1% |
203.6 |
3 |
2.1% |
203.6 |
3 |
2.1% |
203.6 |
|
Batching Plan |
1 |
8.3% |
0 |
1 |
8.3% |
0 |
1 |
8.3% |
0 |
2 |
9.1% |
0 |
|
Concrete Pump |
1 |
97.00% |
0 |
1 |
96.00% |
0 |
1 |
97.00% |
0 |
1 |
97.00% |
0 |
|
Truck Mixer |
22 |
86.15% |
0 |
22 |
86.15% |
0 |
22 |
86.15% |
0 |
24 |
86.15% |
0 |
|
Productivity |
0.00021542 |
0.00021552 |
0.00022552 |
0.00022752 |
|||||||||
Cycle Time |
4621 |
4611 |
4530 |
4421 |
|||||||||
Duration of Work |
74273 |
74251 |
74251 |
72174 |
Based on the table
above, it can be seen
that after making improvements using sensitivity analysis, the productivity value increases and the cycle time decreases, but the results
of the improvement
have results that are not much different from the existing conditions.
From the table above, it
can also be concluded that
iteration 3 is the best iteration
to increase productivity.
CONCLUSION
The CYCLONE modeling results
are presented in Figure 3, and Appendix A. Productivity outcomes for Slab Work
Operations using EZSTROBE software were found to be 0.00963 units per hour,
while SIMULINK yielded 0.0106 units per hour. The third iteration offers the
best combination of improvement based on sensitivity analysis regarding optimal
resource combinations and modeled productivity. This
has the potential to enhance productivity values from current conditions and
reduce cycle times.
REFERENCES
Akbarzadeh,
B., Moslehi, G., Reisi-Nafchi,
M., & Maenhout, B. (2019). The re-planning and scheduling of surgical cases in the operating room department after block release
time with resource rescheduling. European Journal of Operational Research, 278(2), 596–614.
https://doi.org/10.1016/j.ejor.2019.04.037
Cheng,
W.-L., Huang, W.-X., & Nian, Y.-L. (2017).
Global parameter optimization and
criterion formula of supercritical carbon dioxide Brayton cycle with recompression.
Energy Conversion and Management, 150, 669–677.
https://doi.org/10.1016/j.enconman.2017.08.055
Choi,
H., Park, M. J., Rho, J. J., & Zo, H. (2016). Rethinking the assessment of e-government implementation in developing countries from the perspective
of the design–reality gap: Applications in the Indonesian e-procurement system. Telecommunications
Policy, 40(7), 644–660.
https://doi.org/10.1016/j.telpol.2016.03.002
Dabirian,
S., Khanzadi, M., & Moussazadeh,
M. (2016). Predicting labor
costs in construction projects using agent-based modeling and simulation. Scientia Iranica, 23(1), 91–101.
Dasović,
B., & Klanšek, U. (2021). Integration
of mixed-integer nonlinear program and project management tool to support
sustainable cost-optimal construction scheduling. Sustainability, 13(21), 12173.
Dehghanimohammadabadi,
M., Keyser, T. K., & Cheraghi,
S. H. (2017). A novel Iterative Optimization-based
Simulation (IOS) framework:
An effective tool to optimize system’s
performance. Computers
& Industrial Engineering, 111, 1–17.
https://doi.org/10.1016/j.cie.2017.06.037
Fulford,
R., & Standing, C. (2014). Construction
industry productivity and the potential
for collaborative practice. International Journal
of Project Management,
32(2), 315–326. https://doi.org/10.1016/j.ijproman.2013.05.007
Gazzola,
F. (2015). Mathematical models
for suspension bridges. Cham: Springer.
Hahnel,
G., Whyte, A., & Biswas,
W. K. (2021). A comparative life
cycle assessment of structural flooring systems in Western Australia. Journal
of Building Engineering,
35, 102109. https://doi.org/10.1016/j.jobe.2020.102109
Hajdu,
M., & Bokor, O. (2016). Sensitivity analysis in PERT networks: Does activity duration distribution matter? Automation in Construction,
65, 1–8. https://doi.org/10.1016/j.autcon.2016.01.003
Kaushal,
A. K., Mittal, M. K., & Gangacharyulu,
D. (2017). Productivity correlation
and economic analysis of floating
wick basin type vertical multiple effect diffusion solar still with waste
heat recovery. Desalination, 423, 95–103.
https://doi.org/10.1016/j.desal.2017.09.016
Nataadiningrat,
B. B., Prabowo, A. W., Rasmawan, I., Putri, A. T.,
Abduh, M., & Wirahadikusumah, R. D. (2020). Analysis of NATM tunneling method using CYCLONE modeling and simulation tools. IOP Conference Series: Materials Science and Engineering, 933(1),
012002.
Negahban,
A., & Smith, J. S. (2014). Simulation for manufacturing system design and operation: Literature review and analysis. Journal of
Manufacturing Systems, 33(2), 241–261.
https://doi.org/10.1016/j.jmsy.2013.12.007
Pang,
Z., O’Neill, Z., Li, Y., & Niu, F. (2020). The role of sensitivity
analysis in the building performance analysis: A critical review. Energy and Buildings, 209, 109659.
https://doi.org/10.1016/j.enbuild.2019.109659
Sinha,
S., & Chandel, S. S. (2014). Review
of software tools for hybrid
renewable energy systems. Renewable and Sustainable Energy Reviews, 32, 192–205.
https://doi.org/10.1016/j.rser.2014.01.035
Suardi, L. R., Gunawan, B., Arifin,
M., & Iskandar, J. (2018). A review of solid waste management in waste bank activity problems. International
Journal of Environment, Agriculture and Biotechnology, 3(4),
264433.
Thürer,
M., Tomašević, I., & Stevenson, M. (2017). On the meaning of
‘waste’: review and definition. Production Planning
& Control, 28(3), 244–255.
Virine,
L., & Trumper, M. (2019). Project decisions: The art and science. Berrett-Koehler Publishers.
Xiang,
D., Liu, S., Li, Y., & Liu, Y. (2022). Improvement
of flexural and cyclic performance
of bridge deck slabs by
utilizing steel fiber reinforced concrete (SFRC). Construction and Building Materials, 329, 127184.
https://doi.org/10.1016/j.conbuildmat.2022.127184
Yan, J., Bi,
S., & Zhang, Y. J. A. (2020). Offloading and resource allocation with general task
graph in mobile edge computing: A deep reinforcement learning approach. IEEE Transactions on Wireless Communications, 19(8), 5404–5419.
Yoo,
Y., Koliou, M., & Yazdani,
N. (2024). Assessing elevated
home slab retrofitting method for residential coastal buildings under hurricane loads. Journal of Building Engineering, 86,
108994. https://doi.org/10.1016/j.jobe.2024.108994